Project Description
This project includes street reconstruction and minor pavement widening of State Street from Basin Street to the Inner Loop.
Improvements will also include curb modifications and bump outs at intersections, new sidewalks, driveway aprons, lighting, drainage basins, pavement markings, signing, landscape treatments, and traffic signal improvements.
The project is funded with federal, state, city and county funds.
Project Detour - 2023 Construction Season
Please see our detour map for more information.
Project Team
- City of Rochester
- Monroe County
- New York State Department of Transportation
- Federal Highway Administration
- Genesee Transportation Council
- Design Consultant: Labella Associates
Key Stakeholders
- C4 Center City Community Coalition
- Rochester Downtown Development Corp.
Project Documents
Public Involvement
Public Meeting #2 was held on Zoom, on Thursday, June 3, 2021
Public Meeting #1 was held on Wednesday, September 23, 2020 at 5:30pm via Video/Phone Conference.
Anticipated Project Schedule
Preliminary Design: |
2020 |
Final Design: |
2021 |
Bidding and Award: |
Winter 2021 |
Begin Construction: |
Summer 2022 |
Construction Substantial Completion: |
Fall 2023 |
Questions?
Please see the Street Beat webpage for weekly construction updates and current contact information.