Cobbs Hill Neighborhood Infrastructure Projects

About the Projects

 
There are three projects occurring in the Cobbs Hill Neighborhood in 2015 and 2016.


Cobbs Hill / Nunda Neighborhood Street Lighting Project

The scope of the work consists of installing 86 new concrete lighting poles, new fixtures and conduit system. It is intended to utilize as much of the existing conduit system as possible by using trenchless technology to reduce the impact to the surrounding areas. The work also includes replacement of hazardous sidewalks in select locations, drainage improvements and installation of ADA compliant sidewalk access ramps.

  • Cobbs Hill Dr (Highland Ave – Hillside Ave)
  • Bengal Terr (South End – Hillside Ave)
  • Rosegrey Terr (San Gabriel Dr – Beckwith Ter)
  • San Gabriel Dr (Cobbs Hill Dr – Winton Rd)
  • Castlebar RD (Cobbs Hill Dr – Winton Rd)
  • Nunda Blvd (Cobbs Hill Dr – Winton Rd)
  • Beckwith Terr (Cobbs Hill Dr – Winton Rd)
  • Pinnard St (Bengal Ter – Cobbs Hill Dr)

 

Cobbs Hill Drive Highland to Hillside Rehabilitation Project

The proposed improvements include new granite stone curbs, underdrain, spot concrete sidewalk replacement, replacement of some driveway aprons, replacement of the water main between Pinnard St and Hillside Ave, catch basins, lawn restoration, and partial pavement realignment in the vicinity of 154 Cobbs Hill Dr, to eliminate the dead end stub.


2015 Residential Milling and Resurfacing Program Phase 2

Work within the Cobbs Hill Neighborhood consists of Milling and Resurfacing:

  • Cobbs Hill Dr (Highland Ave – Hillside Ave)
  • Rosegrey Terr (San Gabriel Dr – Beckwith Ter)
  • Nunda Blvd (Cobbs Hill Dr – Winton Rd)
  • Chadbourne Rd (Highland Ave – City Line)

And the installation of a Bike Boulevard on Hillside Side Drive from the City line over the Colby Street Pedestrian Bridge.  See the project webpage for more information.


 

Project Materials/Documents

Project Plans 

Project Updates

Vanguard Engineering will be providing inspection services for the City of Rochester for both the street lighting project and the rehabilitation project, they are keeping a Project Blog to help keep residents informed of construction activities.
 

Community Participation Opportunities

  • A Public Meeting of the proposed Bike Blvd is being scheduled
  • A Public Informational Meeting was held for the Cobbs Hill / Nunda Neighborhood Street Lighting Project on May 28, 2015
  • A Public Meeting was held for the Cobbs Hill / Nunda Neighborhood Street Lighting Project on October 14, 2014
     

Project Timeline

 

Cobbs Hill / Nunda Neighborhood Street Lighting Project  June thru Oct 2015  
Cobbs Hill Drive Highland to Hillside Rehabilitation Project    Fall 2015 thru Spring 2016 
2015 Residential Milling and Resurfacing Program Phase 2  Fall 2015 thru Spring 2016 

Questions/Comments?

If you have questions or need more information, contact City Project Engineer, Mr. Frank Bonn, at (585)428-8257.