East Main Street Improvements

About the Project

The City of Rochester is reconstructing a section of East Main Street between N Goodman St and Culver Rd, including pavement reconstruction, new granite curbing, new concrete sidewalks and driveway aprons, new water main, new street lighting and landscaping. Reconstruction of the roadway will improve the ride quality and reduce ongoing maintenance costs. Handicap accessibility will be upgraded as ADA and pedestrian access will be investigated and improvements made in this project where practically feasible and scheduled for the future where not feasible.

 

Documents

 

Public Meeting on June 23, 2020

Public Meeting on January 23, 2020

Public meeting on February 28, 2019

 Stakeholder meeting on October 18, 2018

Project Team


Public Participation

A Public Meeting was held on January 23, 2020.

A preliminary design public informational meeting was held on February 28, 2019.

 

Schedule

Preliminary Design 2018
Final Design 2019
Construction 2020-2021

 

Questions

 questions should be emailed to the City's project manager, Mr. Timothy Hubbard.