About the Project
The Lyell Avenue Improvement Project is a milling and resurfacing project on Lyell Ave between State St and Fairgate St.
The following improvements will be made:
- Milling and resurfacing of roadway with spot pavement reconstruction
- Spot curb replacement
- Spot concrete sidewalk replacement
- Updating and installing sidewalk accessible ramps
- Catch basin and manhole adjustments
- Lawn restorations as required by construction activities
Project Documents
Project schedule
Preliminary Design |
Summer 2018 |
Final Design Plans |
January 2019 |
Street Construction |
Spring - Fall 2020 |
Questions/Comments?
If you have questions or would like additional information, contact the City’s Project Manager, Donna L Clements, PE at 428-6601 or email her.