2024 State Touring Routes Project


Project Description:

This is a State Touring Route funded project that includes two streets in the City of Rochester:

  • W Main Street between W Broad Street and Churchlea Street
  • S Plymouth Avenue between Ford Street and Genesee Street

The project will include, but is not limited to milling and resurfacing of the pavement, spot curb and sidewalk replacement, installation or upgrade of sidewalk curb ramps, replacement of traffic pavement markings, and adjustment and repair of manholes, catch basins, and water valve castings. The project also includes recommendations for lane reductions and parking regulation changes on West Main Street, bicycle accommodations, curb bump-outs at select locations, and other safety improvements throughout the project corridors. 

Project Team:

  • City of Rochester
  • Monroe County
  • NYS Department of Transportation
  • Design Consultant: Stantec 

Project Location Map:

Public Involvement:

 

Anticipated Project Schedule:

Preliminary Design: July 2023
Final Design: December 2023
Bidding and Award:     Winter 2024
Construction: Spring 2024 to Fall 2025