Today, there is a growing awareness that some homes have lead in their water pipes, fixtures and plumbing. To reduce exposure to lead in drinking water, the City of Rochester has developed a lead service line replacement program with the intent to replace all lead services. Lead presents health concerns for people of all ages, particularly pregnant women, infants and young children. The surest way to protect against lead in water is to get the lead out altogether.
Learn more about drinking water safety
Current Lead Service Line Replacement Projects:
Our contractors will be replacing existing lead, lead lined and galvanized water services from the water main to the curb shut off valve with new polyethylene water service tubing.
The locations for this work have been identified by selecting streets that contain water mains that have been previously cleaned and cement lined and that have an abundance of lead, lead lined, or galvanized water services. Work is expected to continue year round when weather permits and will ramp up during the peak construction season.
Construction work is in progress on the following streets:
Street Name |
Water Work
|
Street / Lawn
Restoration
|
Street Name |
Water Work |
Street / Lawn
Restoration
|
Edgemont Rd. |
Completed
|
Spring 2023 |
Langslow St. |
Completed |
Spring 2023 |
Elmerston Rd. |
Completed |
Spring 2023 |
Stewart St. |
Completed |
Spring 2023 |
Castleman Rd. |
Completed |
Spring 2023 |
May St. |
Completed |
Spring 2023 |
Irvington Rd. |
Completed |
Spring 2023 |
Furman Cres. |
Completed |
Spring 2023 |
Rossiter Rd. |
Completed |
Spring 2023 |
Reservoir Ave. |
Completed |
Spring 2023 |
Redfern Dr. |
Completed |
Spring 2023 |
Laney Rd. |
Completed |
Spring 2023 |
Rosemont St. |
Completed |
Spring 2023 |
Azalea Rd. |
Completed |
Spring 2023 |
Fort Hill Ter. |
Completed |
Spring 2023 |
Meadowbrook Rd. |
Completed |
Spring 2023 |
Warren St. |
Completed |
Spring 2023 |
Linden St. |
Completed |
Spring 2023 |
Boothe St. |
Completed |
Spring 2023 |
Cypress St. |
Completed |
Spring 2023 |
Southview Ter. |
Completed |
Spring 2023 |
Cook St. |
Completed |
Spring 2023 |
Westview Ter. |
Completed |
Spring 2023 |
Gold St. |
Completed |
Spring 2023 |
Alpine St. |
Completed |
Spring 2023 |
Hickory St. |
In Progress |
Spring 2023 |
Avenue A |
In Progress |
Spring 2023 |
|
|
|
Project Documents:
View the Fall 2021 project area map. View the 2022 Spring 2A project area maps.
Lead Service Line Replacement Projects for Fall / Winter 2022 - 2023
Click Here for the 2022 Spring 2A Lead Service Line Replacement Project public meeting presentation.
Approximately one week before construction begins on your street, a copy of an Advance Construction Notice will be distributed to each property by door hanger.
The remaining schedule for the 2022 Spring 2A project is:
Streets |
Anticipated Dates |
Avenue A, Avenue B, Avenue C, Morril St., Hollenbeck St., Bleile, Belfour, and OK Terrace |
January - February 2023 |
Avenue E, Rialto St., Mazda Terrace, Malling Dr., and Dorbeth Rd. |
February - March 2023 |
Northview Terrace, Saranac St., Carthage St., Hooker St., Whittier Park, and Teralta St. |
March - April 2023 |
NYE Park, Strong St., Tyler St., and Requa St. |
April - June 2023 |
*Please note that these dates may change due to unforeseen weather conditions.
Questions?
Please contact Project Manager Nick Wynne at (585) 428-7049 or by email.