Project Description
This
is a milling and resurfacing project consisting of the following street segments
located in the City of Rochester:
-
Park
Avenue (Alexander Street to East Avenue)
- St.
Paul Street (Lowell Street to Riverbank Place)
- St.
Paul Street (Norton Street to Tyler Street)
- Monroe Avenue at Sumner Park (safety improvements only)
This
project involves milling off the old pavement surface and paving a new surface.
Street improvements will also include spot curb and sidewalk replacements,
accessible curb ramp replacements, traffic signal and sign improvements,
upgrades to catch basins and manhole frames and covers, new pavement markings, bus
stop landing pads, minor tree plantings and / or removals, curb bump-outs, and
improvements to bicycle and pedestrian facilities. Some improvements may affect existing on-street parking.
Project Team
-
City of Rochester
- Monroe County
- Design Consultant: Barton & Loguidice
- Contractor: To be determined
- Construction Inspection: To be determined
Key
Stakeholders
Southeast
Neighborhood Service Center
Northeast
Neighborhood Service Center
14621 Community Rising
Ibero-American Action League
ABC Streets Neighborhood Association
Park
Avenue Neighborhood Association
Park
Avenue Merchants Association
Park-Meigs
Neighborhood Association
Barrington
Street Neighbors
Berkeley
Street Neighbors
Public Involvement
Nov. 15, 2023: Park Avenue Public Information Meeting (Public Notice)
Sept. 12, 2023: Park Avenue Public Information Meeting (Public Notice)
Aug. 30, 2023: St. Paul Street Public Information Meeting (Public Notice)
You can find updates on this project at this webpage, as well as through the Instant Input app, available at the Apple App Store or Google Play.
Anticipated Project Timeline
Preliminary
Design: Spring / Summer 2023
Final
Design: Fall 2023
Bidding
and award: Winter 2023 to Spring 2023
Construction:
Spring 2024 to Fall 2024 (some work may continue into 2025)
Project Documents
Project Location Maps
Nov. 15, 2023: Park Avenue Public Information Meeting Public Notice
Nov. 15, 2023: Park Avenue Public Information Meeting Presentation
Nov. 15, 2023: Park Avenue Public Information Meeting Roll Plots:
Alexander Street to Barrington Street
Edgerton Street to Homer Street
Homer Street to East Avenue
Sept. 12, 2023: Park Avenue Public Information Meeting Notes
Sept. 12, 2023: Park Avenue Public Information Meeting Presentation
Sept. 12, 2023: Park Avenue Public Information Meeting Roll Plot (DRAFT)
Sept. 12, 2023: Park Avenue Public Information Meeting Public Notice
Aug. 30, 2023: St. Paul Street Public Information Meeting Notes
Aug. 30, 2023: St. Paul Street Public Information Meeting Presentation
Aug. 30, 2023: St. Paul Street Public Information Meeting Roll Plot (DRAFT)
Aug. 30, 2023: St. Paul Street Public Information Meeting Public Notice
July 21, 2023: Park Avenue Stakeholder Meeting Presentation
July 21, 2023: Park Avenue Stakeholder Meeting Summary
July 12, 2023: St. Paul Street Stakeholder Meeting Presentation
July 12, 2023: St. Paul Street Stakeholder Meeting Summary
Questions?
For
questions or comments, please contact:
David
Riley, AICP
Project
Manager
david.riley@cityofrochester.gov
585-428-6978