Street Construction Updates (Street Beat)

 

 Street Name  Project Description Current Work Contractor Expected Completion Traffic / Parking Restrictions Project Contact Information
ALL PROJECTS FOR MEDIA INQUIRES:         For all MEDIA INQUIRIES, please contact the City's Communications Bureau at (585) 428-7135.
ANY CONSTRUCTION FOR GENERAL CITY CONSTRUCTION INQUIRES NOT LISTED HEREIN:         For public works construction related questions that are not covered in this listing, please contact Andy Wojewodzic, Manager of Construction at (585) 428-6523
Aqueduct Street (Main St to Bank Place) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 05/26/23: Private utility work has commenced. City's contractor anticipated to start on or about mid June, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Bank Place (Exchange Blvd to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 05/26/23: Private utility work has commenced. City's contractor anticipated to start on or about mid June, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Basin Street (Exchange Blvd to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 05/26/23: Private utility work has commenced. City's contractor anticipated to continue rebuild of Basin Street the week of June 5, 2023.

Basin Street to be closed for several weeks. 

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Beachwood Neighborhood (Webster Ave to Culver Rd : East Main St to Bay Rd) This project consists of the construction of new ADA curb ramps including new granite curbing, underdrain, concrete, and embedded detectable warning surfaces. New catch basins will be installed at select locations, and other catch basins may receive new frames and grates. 
Updated 06/01/23:  Contractor to begin curb ramp excavation on north side of Hayward Ave on June 5, 2023.

Project Webpage

Millennium Construction Fall 2023

See or call onsite representative Bill Hughes at (585) 370-9665 or call City Project Manager Sam Giovino at (585) 428-6704.

Field Office location TBD. 
Brooks Avenue (Genesee Park Blvd. to Genesee St.) Scope: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new  traffic loops, pavement markings, and signs. Updated 5/26/23: City's contractor expected to commence work in June 2023.

Project Webpage
Ramsey Constructors Fall 2023   See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
Browns Race (Platt Street to Furnace Street) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 5/26/23: City's contractor expected to commence work in June 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   Call Marcus Cox, City Project Manager at (585) 428-8253.
Charles Carroll Plaza/Sister Cities Bridge This project consists of the construction of a new pedestrian access connection from the upper level of the Charles Carroll Park Plaza to the existing Sister Cities Bridge and improvements to the lower walkway along the Genesee River.
Updated 05/26/23:  Contractor has begun work on the plaza and sister cities bridge.  Contractor work zone includes the walkway along the Genesee River from Main St to Andrews St.  Access to this area will be restricted until at least winter 2023.  Sidewalk on the south side of Andrews St is closed from State St to St Paul Blvd due to this project.

Project Webpage  

Crane Hogan Structural Services, Ferrauilo Plumbing and Invictus Electrical Fall 2023 Occasional lane closures and parking restrictions on adjacent streets.

See or call on site representative Jeff Buzzard (585) 505-8885, or call Matt Putnam, City Project Manager at (585) 428-7494.
Chestnut Street (E. Broad Street to E. Main Street)      Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage. Updated 06/01/23: Contractor working on utility adjustments in the roadway. 

Project Webpage
Villager Construction Spring 2023 Occasional Lane Shifts  See or call onsite Representative Bill Hughes (585) 370-9665, or call City Project Manager Sam Giovino at (585) 428-6704.

Field office located at 400 Chestnut St, Suite 100.  
Culver Road (Garson Ave to Laurelton Rd)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 06/01/23: Contractor working on sidewalk and curb excavation once utility locates clear. 

Project Webpage
Keeler Construction      Fall 2023   See or call onsite representative Tanya Pace at (585) 491-4498 or call City Project Manager, Sam Giovino,  at (585) 428-6704.

Field Office located at 311 Alexander Street, Suite 215.
Culver Road (Clifford Ave to Norton St)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 06/01/23: Contractor working on sidewalk and curb excavation once utility locates clear. 

Project Webpage
Keeler Construction  Fall 2023   See or call onsite representative Tanya Pace at (585) 491-4498 or call City Project Manager, Sam Giovino,  at (585) 428-6704.

Field Office located at 311 Alexander Street, Suite 215.
East Avenue (Culver Rd to Probert St) Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 06/01/23: Contractor working on curb bump outs at East Blvd. 

Project Webpage
Keeler Construction Fall 2023   See or call onsite representative Tanya Pace at (585) 491-4498 or call City Project Manager, Sam Giovino,  at (585) 428-6704.

Field Office located at 311 Alexander Street, Suite 215.

East Avenue (E. Main Street to Alexander Street) 
Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage. Updated 06/01/23: Contractor to completing roadway adjustments and final miscellaneous contract items. 

Project Webpage
Villager Construction    Fall 2022 Occasional lane closures.      See or call onsite Representative Bill Hughes (585) 370-9665, or call Sam Giovino, City Project Manager at (585) 428-6704.

Field office located at 400 Chestnut St, Suite 100. 
East Main Street (North Goodman St to Culver Rd) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 5/26/23: Punch list work is ongoing and expected to be completed by 7/1/23.

Project Webpage
Villager Construction Fall 2022 Occasional lane closures and parking restrictions See or call onsite Representative Sid Reedhead (585) 355-4336, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 274 North Goodman St, Room 264 Village Gate, Rochester, NY 14607 
Elmwood Avenue (Mt Hope Ave to South Ave) Work involves: full depth reconstruction of Elmwood Avenue, from Mt. Hope Ave to South Ave, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.  Updated 06/01/23:  Minimal construction impacts on Elmwood Ave. Roadwork is mostly complete. Sub contractor working on signals at South Ave intersection.

Project Webpage
Sealand Contractors Corp.       Fall 2023 Occasional Lane Closures and parking restrictions      See or call onsite Representative Mike Melino (585) 430-1826, or call Sam Giovino, City Project Manager at (585) 428-6704.

Field Office location 1000 Elmwood Avenue, Suite 300.
Erie Harbor / Genesee Gateway Park (Ford Street to 151 Mt Hope Avenue)      Work involves reconstruction of the Genesee Gateway Park, with updated pathways, new one-of-a-kind Timber playground, basketball courts, hand-carry kayak launch, landscaping features and seating/picnic areas.      
Updated 06/01/23: Contractor working on placing dolomite stone, tree plantings and miscellaneous site work. 

Project Webpage

Trail Detour in place. Detour will take you to Mt Hope Avenue and back to the trail around the construction site. 
Ramsey Constructors      Fall 2023 Trail Detour See or call onsite Representative Sean Schumacher (585) 330-9242, or call Sam Giovino, City Project Manager at (585) 428-6704.

 

Exchange Street (Ford St to S. Plymouth Ave)
This work is part of the West River Wall Improvements Phase I
Updated 5/26/23: River trail is now open for the length of the project. The contractor will be on site during the next few weeks working on final clean up, art work  and landscaping

All lanes are open on Exchange St. Northbound from Ford St to S. Plymouth Ave.  

Project Webpage

Ramsey Constructors Summer 2023  
See or call onsite representative Brian Hosmer (585) 662-9204 or call Frank Bonn, City Project Manager at (585) 428-8257
 
Farmington Road (Wyand Crescent to Winton Road)   The scope of work consists of full pavement reconstruction, new granite curbs, spot sidewalk replacement, curb ramp upgrades, new driveway aprons, signage and pavement markings, new water services, repairs of manholes, and new speed humps.  Updated 5/26/23: Curb removal and water service work started.  Utility work is ongoing.

Project Webpage
Nardozzi Companies Fall 2023 Occasional lane, sidewalk, and parking closures. See or call onsite Representative Jeremy Kimble (585) 427-0320 x16, or call Marcus Cox, City Project Manager at (585) 428-8253.
Furnace Street (Browns Race to Mill Street) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 5/26/23: City's contractor expected to commence work in June 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   Call Marcus Cox, City Project Manager at (585) 428-8253.
Graves Street (Main St to Race St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 05/26/23: Private utility work has commenced. City's contractor anticipated to start on or about mid June, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk, and parking closures.
See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Hazardous Sidewalk Replacement, Northwest Quadrant, 2023 Phase 4 Repair and replace hazardous sidewalk in sectors 1 & 2, and 21 - 29 of the northeast and northwest quadrants of the City.  Bordered by Clifford Ave.,  Clinton Ave. and the River.  norhtwest sectors bordered by Ridgeway Ave., West City Line, the Lake and the River.  Updated 5/26/23: This project will replace hazardous sidewalks in the listed sectors.  Work is almost complete in sectors 1 & 2 in the northeast quadrant.  Work is underway in sectors 21&22 in the NW quadrant.

Project Webpage
Espana Construction Fall 2023 Occasional sidewalk closures and possible limited access to driveways.  See or call on site representative John Knapp (585) 370-1794, or call Frank Bonn, City Project Manager at (585) 428-8257.
Jefferson Avenue (Main St. to Champlain St.) Scope involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, spot sidewalk,  curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, pavement markings. Updated 05/26/23: Contractor is replacing curb and sidewalk  and will start on drainage work and preparing for milling and resurfacing in the few weeks.  

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
Orange and Saxton Street Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage.  Updated 5/26/23:  City's contractor has completed all work.  .  RG&E and their contractors  are still working on the underground electrical system.  

Project Webpage
Villager Construction, Inc. Fall 2022   See or call on site representative Karen Montgomery (585) 2876898, or call Frank Bonn, City Project Manager at (585) 428-8257.
Pont de Rennes Bridge Work involves structural repairs, bridge deck replacement, lighting replacement, railing modifications, and landscaping improvements. Updated 5/26/23: City's contractor expected to commence work in June 2023.

Project Webpage

Bridge will be closed to pedestrian traffic from June 2023 through the end of 2024.
Cold Spring Construction Company Fall 2024   Call Marcus Cox, City Project Manager at (585) 428-8253.
Platt Street (Mill Street to Browns Race) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 5/26/23: City's contractor expected to commence work in June 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   Call Marcus Cox, City Project Manager at (585) 428-8253.
Race Street (Graves St to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 05/26/23: Private utility work has commenced. City's contractor anticipated to start on or about mid June, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk, and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Reynolds Street (Seward St. to W. Main St.) Scope of work is the installation of Speed Humps and associated signs.  Updated 05/26/2023:  Contractor will start work on the installation of Speed Humps on 5/31/23

Project Webpage
Ramsey Constructors Spring 2023   See or call on site representative Karen Montgomery (585) 287-6898, or call Frank Bonn, City Project Manager at (585) 428-8257
South Avenue (Elmwood Ave to East Henrietta Rd)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 06/01/23: Contractor to begin construction operations September 2023. Exact start date TBD. 

Project Webpage
Keeler Construction Fall 2023   See or call onsite representative Tanya Pace at (585) 491-4498 or call City Project Manager, Sam Giovino,  at (585) 428-6704.

Field Office located at 311 Alexander Street, Suite 215.
South Avenue (Elmwood Ave to Bellevue Dr)  Work involves: full depth reconstruction of South Avenue, from Elmwood Ave to Bellevue Drive, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.  
Updated 06/01/23:  Contractor working on placing water main on west side of road near Elmwood Ave and roadway boxout from Bellevue to Highland on the east side of the road. 

Expect delays and new traffic pattern. 

Project Webpage

Sealand Contractors Corp.       Fall 2023 Daily lane closures and parking restrictions.  See or call onsite Representative Mike Melino (585) 430-1826 , or call Sam Giovino, City Project Manager at (585) 428-6704.

Field Office location 1000 Elmwood Avenue, Suite 300.
State Street (Basin St to the Inner Loop) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 05/26/23: City's contractor is continuing on sidewalk replacement on the west side of the street.

State Street, (from the Inner Loop to Broad Street), will be one-way for southbound traffic and remain this way through late November 2023. Detour will be posted for north bound travel. 

NOTE: CONSTRUCTION TO CONTINUE TILL THE END OF THE 2023 CONSTRUCTION SEASON. 

Project Webpage
Villager Construction, Inc. Fall 2023  Daily lane closures and parking restrictions See or call on site representative Paul Winterkorn (585) 298-2387, or call Matt Putnam, City Project Manager at (585) 428-7494.
Thurston Road (Genesee Park Blvd. to Arnett Blvd.) Scope: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new  traffic loops, pavement markings, and signs. Updated 5/26/23: Contractor will  be off site the week on 5/29 to 6/2. 

Project Webpage
Ramsey Constructors, Inc. Fall 2023 Occasional lane, sidewalk and parking closures See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
University Avenue (Culver Rd to Blossom Rd) Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations.
Updated 06/01/23: Contractor preparing road for milling and resurfacing. 

Expect traffic delays and lane shifts.

Project Webpage 

Keeler Construction Fall 2023 Occasional lane, sidewalk, and parking closures. See or call onsite representative Tanya Pace at (585) 491-4498 or call City Project Manager, Sam Giovino,  at (585) 428-6704.

Field Office located at 311 Alexander Street, Suite 215.
Waring Road (Culver to Norton) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and bicycle facilities.  Updated 5/26/23:   City's contractor has completed all major work, minor  landscape work will continue thru this summer.  

Project Webpage

Ramsey Constructors, Inc. Fall 2022   See  or call onsite Representative Joe Mancini(585) 319-3618, or call Frank Bonn, City Project Manager at (585) 428-8257.
Wyand Crescent (Merchants Road to City Line) The scope of work consists of full pavement reconstruction, new granite curbs, spot sidewalk replacement, curb ramp upgrades, new driveway aprons, signage and pavement markings, new water services, repairs of manholes, and new speed humps. Updated 5/26/23: Curb removal and water service work started.  Utility work is ongoing.

Project Webpage
Nardozzi Companies Fall 2023 Occasional lane, sidewalk, and parking closures. See or call onsite Representative Jeremy Kimble (585) 427-0320 x16, or call Marcus Cox, City Project Manager at (585) 428-8253.

Back to Street Beat main page.