Street Construction Updates (Street Beat)

 

 Street Name  Project Description Current Work Contractor Expected Completion Traffic / Parking Restrictions Project Contact Information
ALL PROJECTS FOR MEDIA INQUIRES:         For all MEDIA INQUIRIES, please contact the City's Communications Bureau at (585) 428-7135.
ANY CONSTRUCTION FOR GENERAL CITY CONSTRUCTION INQUIRES NOT LISTED HEREIN:         For public works construction related questions that are not covered in this listing, please contact Andy Wojewodzic, Manager of Construction at (585) 428-6523
Broad St. (Broad St Bridge to South Ave) This work is part of the Rundel Library Structural Improvements Phase IV Project. Updated 5/20/22: Site work to continue May 23, 2022, traffic pattern will remain.  Crane-Hogan Structural Systems      Spring 2022 Right turn lane closed and bike lane closed off peak hours.       See  or call onsite Representative John Picard (585) 454-6110, or call Matt Putnam, City Project Manager at (585) 428-7494.
Charles Carroll Plaza/Sister Cities Bridge This project consists of the construction of a new pedestrian access connection from the upper level of the Charles Carroll Park Plaza to the existing Sister Cities Bridge and improvements to the lower walkway along the Genesee River.
Updated 5/20/22:  Contractor has begun work on the plaza and sister cities bridge.  Contractor work zone includes the walkway along the Genesee River from Main St to Andrews St.  Access to this area will be restricted until at least winter 2023.  Sidewalk on the south side of Andrews St is closed from State St to St Paul Blvd due to this project.
Crane Hogan Structural Services, Ferrauilo Plubming and Invictus Electrical Fall 2023 Occasional lane closures and parking restrictions on adjacent streets.

See or call on site representative Jeff Buzzard (585) 505-8885, or call Matt Putnam, City Project Manager at (585) 428-7494.
East Main St (North Goodman St to Culver Rd) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 5/20/22:  Contractor is beginning boxout and reconstruction of the westbound lane of the roadway.  Uneven pavement will be present during boxout.

Expect traffic delays and lane shifts daily.
Villager Construction Fall 2022 Daily lane closures and parking restrictions See or call onsite Representative Sid Reedhead (585) 355-4336, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 274 North Goodman St, Room 264 Village Gate, Rochester, NY 14607 
Elmwood Avenue (Mt Hope Ave to South Ave) Work involves: full depth reconstruction of Elmwood Avenue, from Mt. Hope Ave to South Ave, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.  Updated 05/20/22:  Water work at Southview and Westview. Contractor to work on drainage structures as well. 

Expect traffic delays and lane shifts daily.

Sealand Contractors Corp.       Fall 2023 Daily Lane Closures and parking restrictions      See or call onsite Representative Mike Melino (585) 430-1826, or call Sam Giovino, City Project Manager at (585) 428-6704.

Field Office location 1000 Elmwood Avenue, Suite 300.

 

Exchange St.(Ford St to S. Plymouth Ave)
This work is part of the West River Wall Improvements Phase I
Updated 4/25/22: River trail closed from Fitzhugh Place to S. Plymouth Ave, detour in place.   Construction is starting back up this week to complete the trail and other features across from Fitzhugh Place. 

All lanes are open on Exchange St. Northbound from Ford St to S. Plymouth Ave.  Be alert for bicycles in the roadway.

Ramsey Constructors Summer 2022 Occasional lane closures & parking restrictions
See or call onsite representative Brian Hosmer (585) 662-9204 or call Frank Bonn, City Project Manager at (585) 428-8257
 
Field Office is located at 232 S Plymouth Ave basement level.
N. Goodman St. (Peck St. to Bay St. and Clifford Ave. to Norton St.) Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage. Updated 5/20/22: Contractor is beginning sidewalk removal and reconstruction on the east side of the street.  Villager Construction      Fall 2022 Occasional sidewalk closures and possible limited access to driveways. See or call onsite Representative Bill Hughes (585) 370-9665, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 400 Chestnut St, Suite 100.
Hazardous Sidewalk Replacement, Northwest Quadrant, 2022 Phase 3 Repair and replace hazardous sidewalk in sectors 15-20 of the northwest quadrant of the City.  Bordered by Rochester and Southern Railroad,  Driving Park Ave., The River and Winchester St. Updated 4/25/22: Construction will start in May  2022.  Espana Construction Fall 2022 Occasional sidewalk closures and possible limited access to driveways.  See or call on site representative John Knapp (585) 370-1794, or call Frank Bonn, City Project Manager at (585) 428-8257.
Main Street Streetscape & Pedestrian Wayfinding, Phase II The scope of work consists of replacement of the existing streetscape between Exchange Boulevard/State Street and South Avenue/St. Paul street. Updated 5/20/22: Sidewalk removals and replacement to continue the week of May 23, 2022. 

Expect delays. 
Sealand Contractors Corp. Winter/Spring 2022      Daily lane closures and parking restrictions for full project corridor. See or call on site representative Tim Sherwood (585) 376-2140, or call Matt Putnam, City Project Manager at (585) 428-7494.
Orange and Saxton Streets Rehabilitation Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage.  Updated 4/25/22:  City's contractor has started construction on Orange Street, expect delays.  Utilities are finishing their work on Saxton Street and the contractor will be starting curb and sidewalk work in May.  Villager Construction, Inc. Fall 2022 Occasional lane and sidewalk closures for the project corridor. See or call on site representative Karen Montgomery (585) , or call Frank Bonn, City Project Manager at (585) 428-8257.
Ridgeway Avenue (Latona Rd Mt. Read Blvd) This project consists of constructing a portion of the future Eastman Trail corridor, including 0.77 miles of 8' wide concrete trail and lane reconfiguration on 0.25 miles of roadway to include bike lanes. The construction of the concrete trail will generally require asphalt driveway apron replacement, gas valve box adjustments, mailbox replacement and signage relocation. Two landscaped bench areas will be installed along the concrete trail. The construction of bike lanes will generally require striping modifications, adjustment of drainage structure frames and replacement of grates, and removal and installation of signage. 

Also included in the project is the modification of the bridge carrying Ridgeway Avenue over Kodak Park (BIN 3211140). The intent is to widen the existing 5' wide sidewalk on the north side to 12' wide. This will require removal and replacement of bridge and adjacent roadway curb, closed drainage modifications, guide railing replacement, bridge join repair and pavement marking reconfiguration. 
Updated 05/20/22: Final sidewalk restoration to take place, miscellaneous topsoil and site clean-up. 

Extended lane shift for westbound traffic will be in place during bridge work. Expect delays. 
Villager Construction, Inc. Fall 2022 Occasional lane and sidewalk closures for the project corridor.  See or call on site representative Chad Stevens (315) 243-1943 , or call Sam Giovino, City Project Manager at (585) 428-6704.
Rochester Riverway Trail  (Downtown)    Trail closures associated with downtown ROC The Riverway Projects
Updated 3/29/22: Trail is closed between Fitzhugh Place and S. Plymouth Ave. on the west side due to the West River Wall project.  Trail detour routes pedestrians along the west side of Exchange Blvd from Ford St to Court St in both the northbound and southbound directions.
 

East side river trail is open from Ford St to Court St.

 
Ramsey Constructors (West River Wall)
West Side closed until Spring 2022   Call Frank Bonn, City Project Manager at (585) 428-8257
South Avenue (Elmwood Ave to Bellevue Dr) Work involves: full depth reconstruction of South Avenue, from Elmwood Ave to Bellevue Drive, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.   Updated 05/20/22: Contractor to work on water services at north end of job (Bellevue Dr). 

Expect traffic delays and lane shifts daily.

Sealand Contractors Corp.       Fall 2023 Daily lane closures and parking restrictions.  See or call onsite Representative Mike Melino (585) 430-1826 , or call Sam Giovino, City Project Manager at (585) 428-6704.

Field Office location 1000 Elmwood Avenue, Suite 300.
State Street (Basin St to the Inner Loop) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 5/20/22: Utility work continuing the week of May 23, 2022.

City's contractor anticipated to begin in June 2022.
Villager Construction, Inc. Fall 2023 Daily lane closures and parking restrictions See or call on site representative Paul Winterkorn (585) 298-2387, or call Matt Putnam, City Project Manager at (585) 428-7494.
Various Locations  This work is part of the Local Pedestrian Safety Action Plan project. This project consists of improvements to pedestrian facilities at up over 200 locations throughout the City of Rochester. These improvements include signage and wayfinding devices at intersections, enhanced crosswalk striping, Rectangular Rapid Flashing Beacons, raised table crosswalks and curb bumpouts.  Updated 05/20/22: Contractor not working. 
 
Millenium Construction Inc. Fall 2021 Occasional lane closures and parking restrictions for project corridor. See or Call on-site representative, Lisa Barrett, at (585) 475-1440 or call Sam Giovino, City Project Manager, at (585) 428-6704. 

Field Office located at Stantec Consulting Services, 61 Commercial St, #100.
Weaver Street (Remington St. to Hudson Ave.) Work involves: full depth reconstruction of the existing roadway; storm sewers improvements; new curb; pavement; spot sidewalk replacement; new lighting; signing and trees.  Updated 4/25/22: Utility work is almost complete. 

City's contractor anticipated to begin in May 2022.
Ramsey Constructors, Inc. Fall 2022 Utility work is ongoing with some lane reductions See  or call onsite Representative Jeremy Kimble(585) 953-9374, or call Frank Bonn, City Project Manager at (585) 428-8257.
Waring Road (Culver to Norton) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and bicycle facilities.  Updated 4/25/22:  Contractor is removing the old roadway and constructing new pavement in the south bound direction.  Traffic will be controlled by flaggers in the work zones during the day and two way traffic will resume during non-work hours.  Ramsey Constructors, Inc. Fall 2022 Lane reductions are in place with on street parking restricted. See  or call onsite Representative Joe Mancini(585) 319-3618, or call Frank Bonn, City Project Manager at (585) 428-8257.