Street Construction Updates (Street Beat)

 

Street Name  Project Description Current Work Contractor Expected Completion Traffic / Parking Restrictions Project Contact Information
ALL PROJECTS FOR MEDIA INQUIRES:         For all MEDIA INQUIRIES, please contact City of Rochester Press Officer, Jessica Alaimo at (585) 428-7135.
ANY CONSTRUCTION FOR GENERAL CITY CONSTRUCTION INQUIRES NOT LISTED HEREIN:         For public works construction related questions that are not covered in this listing, please contact Andy Wojewodzic, Manager of Construction at (585) 428-6523
Broad St. (Broad St Bridge to South Ave) This work is part of the Rundel Library Structural Improvements Phase IV Project. Updated 4/9/21: Site work to continue the week of April 12, 2021, traffic pattern will remain.  Crane-Hogan Structural Systems      Fall 2021 Right turn lane closed and bike lane closed off peak hours.       See  or call onsite Representative John Picard (585) 454-6110, or call Matt Putnam, City Project Manager at (585) 428-7494.
Charles Carroll Plaza/Sister Cities Bridge This project consists of the construction of a new pedestrian access connection from the upper level of the Charles Carroll Park Plaza to the existing Sister Cities Brige and improvements to the lower walkway along the Genesee River.
Updated 3/29/21:  Contractor has begun work on the plaza and sister cities bridge.  Contractor work zone includes the walkway along the Genesee River from Main St to Andrews St.  Access to this area will be restricted until at least fall 2021.  Sidewalk on the south side of Andrews St is closed from State St to St Paul Blvd due to this project and the adjacent court house renovations.
C.P. Ward, Inc. and Invictus Electrical Fall 2021 *pending approval of project Phase 2 Occasional lane closures and parking restrictions on adjacent streets. See or call on site representative Mike Lydle (585) 505-8885, or call Marcus Cox, City Project Manager at (585) 428-8253.
East Henrietta Rd (S. City Line / Erie Canal to Westfall Rd) Improvements Work involves: rehab of the existing roadway with pavement widening where required; spot replacement of curb and sidewalk;  new street lighting system; adjustment of manholes and catch basins; new drainage system; and pavement markings. Updated 4/9/21: New traffic signal work to continue the week of April 12, 2021.

Expect traffic shifts daily.
Villager Construction Spring 2021 Daily lane closures.  Expect delays!

See or call onsite Representative David Persons (585) 434-0859 or call Matt Putnam, City Project Manager at (585) 428-7494

Field Office located at 1815 South Clinton Avenue, Suite 220

East Main St (North Goodman St to Culver Rd) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 4/9/21: Water service installation to continue along south side of East Main Street. Utility contractor to continue work on Monday, April 12, 2021.

Expect new traffic patterns.
Villager Construction Fall 2022 Daily lane closures and parking restrictions See or call onsite Representative Sid Reedhead (585) 355-4336, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 274 North Goodman St, Room 264 Village Gate, Rochester, NY 14607 
Exchange St. (Broad St to Court St) This work is part of the Blue Cross Arena Upgrades Project.      Updated 4/9/21: Project to continue the week of April 12, 2021.  Expect a northbound, right lane closure in front of the Blue Cross Arena.  Javen Construction Spring 2021      North bound: East lane closed  See onsite representative or call Matt Putnam, City Project Manager at (585) 428-7494

 

Exchange St.(Ford St to S. Plymouth Ave)
This work is part of the West River Wall Improvements Phase I
Updated 3/29/21: River trail closed from Violetta St to S. Plymouth Ave, detour in place.  Material hauling to and from the site occurring daily.  Be alert for flaggers.

Bicycle lane and shoulder closed on Exchange St. Northbound from Ford St to S. Plymouth Ave.  Be alert for bicycles in the roadway.

Ramsey Constructors Spring 2022 Occasional lane closures & parking restrictions
See or call onsite representative Brian Hosmer (585) 662-9204 or call Marcus Cox, City Project Manager at (585) 428-8253
 
Field Office is located at 232 S Plymouth Ave basement level.
Main Street Streetscape & Pedestrian Wayfinding, Phase II The scope of work consists of replacement of the existing streetscape between Exchange Boulevard/State Street and South Avenue/St. Paul street. Updated 4/01/21: Work expected to commence Late April/Early May 2021.   Winter/Spring 2022      Daily lane closures and parking restrictions for full project corridor. See or call Marcus Cox, City Project Manager at (585) 428-8253
Mount Read Blvd (Buffalo Rd. to Lyell Ave.) This is a NYSDOT - Region 4 project that will resurface  Mount Read Boulevard from Rt 33 (Buffalo Rd) to the CSX Bridge north of Rt 31 (Lyell Ave) and upgrading to a roundabout at the southern limit in the City of Rochester, Monroe County.

Refer to NYSDOT - Region 4 for updates or go to:

https://www.dot.ny.gov/portal/pls/portal/MEXIS_APP.DYN_PROJECT_DETAILS.show?p_arg_names=p_pin&p_arg_values=4940K4

CATCO 
 Fall 2020

 

Jordan Guerrein, PIN-4940K4
NYSDOT Region 4 Public Information Officer
1530 Jefferson Road
Rochester, NY 14623

Phone: 585-272-4818
Mount Hope Ave (Southern City Limit to Rossiter Rd) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 4/9/21: Private utility work will continue the week of April 12, 2021. City construction to continue the week of April 12, 2021.

Expect new traffic patterns. 
Sealand Contractors Corp. Fall 2021 Daily lane closures and parking restrictions See or call onsite Representative Mike Melino (585) 867-9486, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 1769 Mount Hope Avenue Rochester, NY 14620 
Rochester Riverway Trail  (Downtown)    Trail closures associated with downtown ROC The Riverway Projects
Updated 3/29/21: Trail is closed between Ford St and Court St on the west side due to the West River Wall project.  Trail detour routes pedestrians along the west side of Exchange Blvd from Ford St to Court St in both the northbound and southbound directions.
 

East side river trail is open from Ford St to Court St.

 
Ramsey Constructors (West River Wall)
West Side closed until Spring 2022   Call Marcus Cox, City Project Manager at (585) 428-8253
Sager Drive (Culver Road to East Boulevard) Work consists of reconstruction of the existing pavement structure, including new watermain and services, storm sewer work, street lighting and other utilities. Conversion of street to one-way travel in the eastbound direction.     Updated 4/9/21: Work is substantially complete, punch-list and restoration work ongoing.


NEW TRAFFIC PATTERN IN PLACE: ONE WAY STREET FROM CULVER RD TO EAST BOULEVARD

Go to www.vaneng.com & click on current projects for more detailed information. 
Ramsey Constructors      Fall 2020 Occasional lane closures & parking restrictions See or call onsite Representative Jeremy Kimble (585) 427-0320 x16, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 595 Blossom Road, Suite 201
South Ave (Broad St. to Court St.) This work is part of the Rundel Library Structural Improvements Phase IV Project. Updated 4/9/21: Site work to continue the week of April 12, 2021, traffic pattern will remain.  Crane-Hogan Structural Systems Fall 2021 Right (East) curb lane closed for traffic.

See  or call onsite Representative John Picard (585) 454-6110, or call Matt Putnam, City Project Manager at (585) 428-7494.