Aqueduct District Street Improvement Project


RTR Ph 2 page header

Project Description

As a part of the ROC the Riverway initiative, and the overall Aqueduct Reimagined and Riverfront Promenades vision, the Aqueduct District is being transformed into a pedestrian friendly area, while maintaining accommodations for vehicular access.

The project includes street reconstruction and streetscape improvements to Aqueduct Street, Bank Place, Basin Street, Graves Street and Race Street. Aqueduct Street will be converted to one-way southbound, Bank Place will be converted to one-way westbound and a new traffic signal will be placed at the intersection of Bank Place and Exchange Boulevard.

Improvements will also include new sidewalk, curb, curb ramps, driveway aprons, drainage basins, hydrants, lighting, signing, pavement markings, and other various streetscape improvements. Interim improvements to Bank Place are anticipated during this phase of the project. Final improvements to Bank Place will be included in a later phase of the Aqueduct Reimagined and Riverfront Promenades project.

For more information refer to the Aqueduct Reimagined and Riverfront Promenades project webpage at https://www.roctheaqueduct.com/

Project Team

City of Rochester
Monroe County
New York State Department of Transportation
Genesee Transportation Council
Design Consultants: Bergmann, Lu Engineers, WXY, Urban AC, and The Light Practice
Construction Inspection Firm: TBD
Contractor: TBD

Public Involvement

For public involvement related materials refer to the Aqueduct Reimagined and Riverfront Promenades project webpage at https://www.roctheaqueduct.com/

Project Documents


Anticipated Project Schedule (Aqueduct District Street Improvements)

Preliminary Design: Spring 2022 to Fall 2022
Final Design: Fall 2022 to Winter 2022/2023
Bidding and Award: Winter 2022/2023 to Spring 2023
Construction: Spring 2023 to Fall 2023
Final Construction (Bank Place): TBD

For current construction updates refer to the City’s STREET BEAT website.

Questions?

For questions please contact:

Kamal L. Crues, PE
Assistant City Engineer/Project Manager
kamal.crues@cityofrochester.gov

Dominic Fekete, PE
Manager of Street Design
dominic.fekete@cityofrochester.gov
585.428.6767

Andy Wojewodzic
Manager of Construction
andrew.wojewodzic@cityofrochester.gov
585.428.6523